Background

Network Rail required a platform to measure the energy use on 900 rail heater systems across the network.  The system was a complex voltage of 650VDC and had new as well as legacy equipment from a variety of manufacturers.

They did not measure this energy so could not invoice the train companies who operated on the tracks the correct amount of energy.​​​

Solution

Due to the complexity of the roll-out and the various manufacturers we designed and implemented a bespoke system, agnostic to technology and with an asset management front end allowing the asset owner, equipment manufacturer and track side engineers to build, pre-commision, install and commission the systems with minimal effort and fully automate the process.

Conclusion

Network Rail have used our system successfully for the past 7 years allowing them to invoice the train companies for the energy used to heat the tracks during winter.